What construction cleaning services actually include

A room-by-room breakdown of what a final construction clean covers, what is normally excluded, and the items that quietly move onto a separate invoice.

Construction cleaning sits between builders' work and janitorial work, and the boundary is not standardised. Two contractors can both be quoting honestly and mean quite different things.

What follows is what a full final clean normally covers. Use it as a checklist rather than an assumption, because on any given quote at least two of these will be excluded.

Normally included in a final clean

  • All interior glass, including frames, tracks, sills and any remaining protective film or adhesive residue.
  • Cabinetry and joinery cleaned inside and out, including drawer runners and shelf edges.
  • Fixtures, fittings, switch plates, door furniture and handrails wiped and polished.
  • Kitchens and bathrooms cleaned to a finished, ready-to-use state including appliance interiors.
  • Floors cleaned to their finished condition, with the method matched to the material.
  • Light fittings, vents and diffusers dusted or wiped where they are safely reachable.
  • Skirtings, ledges, door tops and other horizontal surfaces where construction dust settles.

Normally excluded, or priced separately

These are the items that turn up as a second invoice. None of them are unreasonable to charge for; the problem is only ever that they were assumed to be included.

Separately billed items and their published costs
ItemPublished cost
Construction debris removal$300 to $1,000
HVAC duct cleaning$200 to $1,000
Window cleaning as a standalone service$150 to $370
Floor stripping and waxing$0.50 to $3.00 per sq ft
Carpet cleaning$40 to $90 per room
Exterior cleaning$125 to $800 or more
Pressure washing$170 to $360

Source: HomeGuide, Post-Construction Cleaning Rates, updated December 2025

The exclusions worth arguing about

Two exclusions cause most of the disputes. The first is paint, adhesive and grout residue on finished surfaces, which some contractors treat as remedial work belonging to the trade that caused it rather than as cleaning. The second is duct cleaning, which matters more than it sounds: a building cleaned to a perfect standard will re-dust itself within days if construction dust is still sitting in the supply ducts.

Both are worth resolving in writing before work starts rather than at the handover inspection.

Get Quotes